Province | Subbasin | % |
---|---|---|
Columbia Plateau | Walla Walla | 100.00% |
Previous: | Next: |
---|---|
63364: 2000-038-01 EXP WALLA WALLA HATCHERY - CTUIR EC/DESIGN SUPPORT |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Provide Technical Review of Final Designs | B: 122. CTUIR input to final design process | 09/30/2019 | ||
Provide Input on EC Activities | D: 165. CTUIR input to EC activities | 12/31/2017 | 12/22/2017 | |
Input to Step decisions provided as needed | E: 196. Input to Steps 2 and 3 review/approval | 09/30/2018 | 09/28/2018 | |
Interim water quality report | H: 165. S.Fork Walla Walla Water Quality Data Collection/Analysis | 07/19/2019 | 07/12/2019 | |
Effective implementation management and timely contract administration | I: 119. Construction Review Budget Package | 09/30/2019 | 09/30/2019 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (Oncorhynchus tshawytscha) - All Populations |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Construction Review Budget Package | 04/01/2017 | ||||||
B | 122 | CTUIR input to final design process | 04/01/2017 | ||||||
C | 122 | CTUIR input to construction process | 04/01/2017 | ||||||
D | 165 | CTUIR input to EC activities | 04/01/2017 | ||||||
E | 196 | Input to Steps 2 and 3 review/approval | |||||||
F | 132 | No Annual progress report required | 04/01/2017 | ||||||
G | 185 | Periodic Status Reports for BPA | 04/01/2017 | ||||||
H | 165 | S.Fork Walla Walla Water Quality Data Collection/Analysis | 04/01/2017 | ||||||
I | 119 | Construction Review Budget Package | 04/01/2017 |